Subject: Legal Notice Regarding Financial Errors, Negligence, and Unfair Demands in the Processing of My Payments for Flat D‑808, Aparna Zenon (Phase 1)
To the Management of Aparna Constructions,My name is Sandeep Chadda, the owner of Flat D‑808 in Aparna Zenon Phase 1. I am issuing this legal notice myself because of the serious lapses, errors, and prolonged negligence I have experienced from your accounts and sales teams since January 2023.
I am not a lawyer, but as a homebuyer affected by these issues, I have every right to demand accountability and resolution. This notice may be placed before the Consumer Court if the matter is not resolved promptly.
1. Background
- I opted for 100% upfront payment to avail the 10% discount offered by Aparna.
- To make this payment, I sold one of my properties and broke fixed deposits.
- On 13 January 2023, I handed over four cheques to your team.
- What followed was months of silence, mistakes, conflicting cost sheets, and repeated follow-ups from my side.
2. Issues I Faced (In Simple, Clear Language)
A. No acknowledgement for months
Despite multiple emails and calls in January, February, and March, I received no confirmation that my payments were processed. This left me anxious and unsure about my financial standing.B. Constant change in staff with no handover
I was forced to deal with five account representatives within months:Madharao → Vijaya → Suraj → Sai → Sridhar
Every time, I had to repeat the entire story. There was no continuity or proper communication on your end.
C. Internal email ID changes caused communication breakdown
I discovered much later that one of your key employees’ email IDs changed internally, which is why he wasn’t receiving my messages. I was never informed about this.D. Repeated errors and contradictory cost sheets
Your accounts department repeatedly sent me wrong cost sheets. These sheets kept changing and demanded:- ₹2,39,215
- ₹1,99,467
- ₹37,000
- ₹1,16,351
E. Unprofessional and insensitive comments
Instead of fixing the issues, I was told:- “Why did you submit cheques?”
- “You should show more patience.”
- “We are not a services company; we do not send reminders.”
F. Excessive follow-ups
Between January and June, I followed up 30–40 times just to understand what was happening with my own money.3. Serious New Issue (19 January): TDS Accounting Error
On 19 January, I was told that:- Aparna had been incorrectly showing ₹58,665 TDS as already paid in the cost sheets.
- This was a long-standing accounting error on your side.
- I am now being asked to pay this amount suddenly before handover.
4. Compensation for Financial Loss Already Incurred
Due to repeated accounting errors and mismanagement, I was earlier forced to pay ₹1,16,351, which arose directly from your incorrect calculations and the delay caused by multiple internal lapses.I want to be very clear:
This amount was paid only because your cost sheets kept changing due to your team’s errors.
Therefore, I am formally requesting that Aparna:
Reimburse the amount of ₹1,16,351
as this financial burden resulted exclusively from your negligence and not from any delay or mistake on my part.This statement uses firmer language, as is appropriate in a legal notice, while still being written in my own voice.
5. What I Expect From Aparna Immediately
I request the following resolutions:- Withdraw the wrongful TDS demand of ₹58,665, as it was Aparna’s internal accounting error.
- Reimburse ₹1,16,351, which I paid earlier due to repeated financial miscalculations by your team.
- Provide a final, accurate, error-free cost sheet reflecting correct charges.
- Confirm in writing that I will not be penalized or charged interest for delays caused solely by Aparna’s internal failures.
- A detailed written explanation of what went wrong and how Aparna plans to prevent such lapses.
6. Notice Period
Please respond to this notice within 15 days from the date of receipt.If no satisfactory response is received within this period, I will proceed to file a formal case in the Consumer Court, seeking:
- Withdrawal of the incorrect TDS demand
- Refund of the earlier ₹1,16,351 paid due to your mistakes
- Compensation for mental harassment and inconvenience
- Recovery of legal and litigation costs
- Any additional relief the Court may grant under the Consumer Protection Act
Sincerely,