    Builder refusing to refund rightful amount after persistent delays in proj3ct completion

    Dear Sir/Madam, I would highly appreciate your support in drafting the legal notice against Presidency Infraheights Private Limited. Kindly note that I have made a total payment of Rs. 38,34,226/= (Rs. 34,23,420 Principal +410,806 GST) from 5th January 2019 until 08 February 2024. This amount...
  2. I

    Builder refusing to refund rightful amount after persistent delays in proj3ct completion

    Hello, I have purchased an apartment in 2019 on deffered payment plan for which I have made a payment of 55% untitl February 2024 based on payent demand from the builder. The project completion was supposed to be June 2023 however due to covid19 related extension approved by RERA, the project...